PROJECT
Leuglay Footbridge -
LOCATION
Sur la rivière Ource -
CLIENT
Ville de Leuglay -
PROJECT MANAGEMENT
Marc Mimram Architecture et Ingénierie -
DATE
1998 -
AREA
Span of 12 meters (oak beam) Width of 2.5 meters -
COST
0.04 M€ - Download the project
The Leuglay footbridge crosses the Ource to reach the forest house. A tree trunk placed above the river forms a founding, simple and natural link.
But here, around the trunk, a dialogue is established, between the tree stump and the galvanized steel corbel arranged in a gentle curve, encountering the risks of the singular trunk. The structure arises from this meeting between nature and manufacturing.